Edward (Ted) Taylor Science and Engineering Building
Otter Statue Installation

A new nine-foot tall otter statue will be installed near the OSU. The statue will be a prominent campus landmark, symbolizing the heartbeat of pride for Cal State Monterey Bay.
Campus Contact
Vera Abou Shakra, Senior Construction Project Manager (831) 582-5141
Project timeline
Oct 2024 - April 2025
Project cost
around $180K
Client
CSUMB Community
Design team
HGHB and E&J Fine Art LLC
Contractor
Otto Construction
Gavilan Hall Bldg 201 Project Update: Entering Schematic Design Phase

The steering committee for the Gavilan Hall Bldg 201 refurbishment project has successfully completed the feasibility phase. We are now moving into the schematic design phase. This marks a significant step forward in transforming the building into a modern dormitory space. The committee is working closely with architects and stakeholders to refine the design and ensure it aligns with both the university’s goals and the needs of future residents. An exciting feature of the design will be a community quad space, designed to encourage interaction and collaboration among residents. Stay tuned for further updates as the project progresses.
Campus Contact
Matt Kelly, Associate Director of Construction (831)582-4304
Project timeline
Fall 2026 Completion Date
Project cost
$18 million
Client
University Corporation
Design team
LPA Design Studios
Contractor
TBD