News

IT update on Zoom phone rollout schedule

October 2, 2023

CSUMB's roll out of the new Zoom phones will be done in a six-stage process. Some phases may go faster than projected, some longer than projected as is the nature of any project. 

Information Technology aims to keep this information as up-to-date as possible during the transition, so visit this page any time to keep apprised of our progress on the Zoom phone roll-out. 

For questions, contact Project Lead Brian Beckman

Pre-phase
Receive and configure hardware
June 9 - June 12, 2023

Test Phase
June 26 - June 30, 2023
Buildings: 41, 41A, 43, 35, 36, 37, 201 (Stateside & KAZU offices)

Phase 1
July 3 - Aug. 4, 2023
Buildings: 1, 13, 27, 28, 29, 30, 32, 44, 45, 45, 46, 47, 48, 49, 50, 58, 59, 100, 490, 690, 
703 (NTF), 702 (AMR), 902, 903c, 904 (BB)

Phase 2
Aug. 14 - Oct. 6, 2023
Buildings: 2, 3, 4, 6, 8, 10, 11, 12, 14, 16, 18, 98, 202, 203, 204, 205, 206, 208, 210, 211, 552

Phase 3
Delayed: Oct. 16 - Dec. 15, 2023
Buildings: 80, 81, 82, 84, 86, 90, 91, 97, 301, 302, 303, ECT, ECS

Phase 4
Delayed: Jan. 2, 2024 - ?
Buildings: 70, 71, 72, 73, 75. 325, 325a, 326, 327, 170

Phase 5
Delayed: new dates to be announced when Phase 4 is complete
Buildings: 21, 23, 53, 504, 506, 508, 1001, 1002, MCOL, 201 (Extended Education and International Programs)

For more information, go to the Zoom phone knowledge base webpage.